What Is a Hindrance Claim in Construction Contracts? Time, Cost and Proof Under Indian Law

By Ujjwal Sharma MCIArb · November 2, 2026 · 13 min read

By Ujjwal Sharma MCIArb (Advocate, Mediator & Arbitrator; Head of Chambers - Sharma Kemp Chambers)

In brief: A hindrance claim is a contractor's claim for extra time, extra money or both, because something the employer was responsible for obstructed the works. Typical examples are a site that was not handed over on time, drawings issued late, approvals held up or instructions that changed midway. The claim is built on the contract and on the Indian Contract Act, 1872, and it succeeds or fails largely on notice, causation and records. This article is written for in-house counsel, project owners, developers, contractors, project and contract managers, claims consultants and lenders' advisers who need a practical understanding of how these claims work in India, what heads of loss are recoverable and what evidence tribunals expect.


What "hindrance" means

In construction, a hindrance is any event, act or omission that obstructs or delays the contractor from carrying out the works in accordance with the programme. The word is used most often in public works contracts, where the engineer-in-charge traditionally keeps a hindrance register in which obstructions are recorded as they occur. But the concept is not confined to government work. Private developers, EPC contracts and infrastructure concessions all deal with the same issue under different labels, such as "employer's risk events", "compensation events" or "delay events".

A hindrance claim is the formal assertion by the contractor that a particular hindrance, for which the employer is responsible, has caused delay or additional cost, and that it is entitled to a remedy.

The two questions every hindrance claim raises

It helps to separate the claim into two distinct questions, because they are decided on different footing.

Question What it decides Typical remedy
Was the contractor delayed, and is it entitled to more time? Whether the completion date moves and whether delay damages can be charged An extension of time (EOT) and relief from liquidated damages
Did the hindrance cost the contractor money, and is that recoverable? Whether the contractor can recover its additional costs Compensation for prolongation and disruption, subject to the contract and the law

A contractor can win the first and lose the second. For instance, an employer may accept that a late drawing delayed the works by six weeks and grant an extension, while rejecting any claim for the contractor's costs during those weeks. Many contracts allow time for neutral events such as exceptional weather but provide no money, whereas employer-caused hindrances more commonly carry both.

Where the right comes from

The contract. Most contracts set out the events that give rise to an extension or compensation, together with a notice procedure. This is the first document to read. Public sector forms usually deal with hindrances and extensions in a single clause, while international forms such as FIDIC separate time and cost entitlements and impose firm notice periods.

The Contract Act. Where the contract is silent, or where the employer has breached it, the general law applies:

  • Section 53 provides that where one party prevents the other from performing the contract, the contract becomes voidable at the option of the party prevented, who is also entitled to compensation for any loss sustained.
  • Section 55 deals with the consequences of failing to perform on time and provides that a party who accepts late performance must give notice of its intention to claim compensation.
  • Section 73 entitles a party who suffers from a breach to compensation for loss that naturally arose in the usual course of things, or that the parties knew when they made the contract would likely result from the breach. It does not permit recovery for remote or indirect loss.

A contractor's hindrance claim is, in legal terms, a claim for breach of the employer's implied obligation to cooperate and to give the possession, information and approvals the contract requires.

Common sources of hindrance

Source Examples
Site and access Late or partial handover of the site, encroachments, disputes with neighbouring owners, delays in land acquisition, lack of access roads
Design and information Late, incomplete or changing drawings and specifications; late approval of samples or shop drawings
Employer supplies Late supply of materials, equipment or drawings which the employer promised to provide
Approvals and utilities Statutory permissions, utilities shifting, clearances that the employer was to obtain
Instructions Variations, suspension orders, stop-work orders, changes in sequence
Payment Late payment that forces the contractor to slow down, where the contract allows for this
Interface Delay by other contractors engaged by the employer

What a contractor can claim

Hindrance claims for money are made under several distinct heads of loss. Tribunals look at each separately, and many awards are reduced or set aside because the heads were bundled together without evidence.

Head of claim What it covers Proof usually expected
Idle labour and plant Cost of workers, supervisory staff and equipment kept on site but unable to work Muster rolls, attendance records, equipment logs, hire invoices, payroll
Extended site overheads Site office, security, utilities, supervision and similar running costs for the delay period Actual cost records, invoices and the programme
Head office (off-site) overheads A share of the contractor's central costs attributable to the prolonged contract Audited accounts, proof of lost turnover or opportunity (see below)
Escalation and price increase Increased cost of materials and labour during the delay period Price indices, invoices, the contract's price variation clause
Financing costs and interest Cost of capital tied up or extended guarantees Bank records, guarantee extension charges, interest calculations
Loss of profit Profit lost on work not carried out (typically on termination or reduction of work) Contract rates, margins and the extent of unexecuted work
Loss of profitability Reduced profit across the business because resources were tied up by the delay Evidence of other work lost, such as declined tenders and turnover figures

Why head office overheads and lost profit are difficult

Indian courts have been cautious about these two heads, and for good reason. A formula can produce a figure, but it cannot prove that the loss was suffered.

The Supreme Court has made the following points in a line of decisions:

  • In A.T. Brij Paul Singh v State of Gujarat (1984), the Court accepted that a contractor who is wrongfully prevented from completing works can expect to earn a profit, and that the loss may be assessed on a broad basis.
  • In McDermott International v Burn Standard (2006), the Court observed that the Contract Act prescribes no single method for computing damages. Formulae such as Hudson, Emden and Eichleay may be used, but they depend on assumptions that must be satisfied, and they should be used with care to avoid double recovery.
  • In Unibros v All India Radio (2023) and Batliboi Environmental Engineers v Hindustan Petroleum Corporation(2023), the Court held that a claim for loss of profitability due to prolongation requires credible evidence. As we read these decisions, the contractor must show that the delay was not its fault, that it is an established contractor, and that it lost other work or profit as a result, for instance by showing declined tenders or a fall in turnover attributable to the delay. If that is not shown, the delay may be treated as merely a delay in receiving money, for which the remedy is generally interest on the capital employed.

The practical message is that a claim built only on a formula is vulnerable. A tribunal may use a formula as a tool, but the contractor still has to prove the facts that make the formula applicable. An award of overheads or lost profit without credible evidence can be challenged under Section 34 of the Arbitration and Conciliation Act, 1996.

The three formulae in outline

Formula Basis Main criticism
Hudson Applies the head office overhead and profit percentage in the contract price to the delay period The percentage may bear no relation to actual overheads, and it risks double counting profit
Emden Uses the contractor's actual overhead and profit percentage from audited accounts Relies on past figures and still presumes that the contractor lost the opportunity to earn them
Eichleay Allocates overhead by the ratio of contract billings to total billings, then converts it to a daily rate Developed in the United States and generally used where lost opportunity cannot be shown; typically applied after completion

Notice, records and the "hindrance register"

Most hindrance claims fail for practical reasons rather than for legal ones.

Notice. The contract will usually require notice of the hindrance within a specified period. Late notice can bar the claim or, at least, weaken it significantly. Contractors should give written notice at the time the hindrance occurs, refer to the relevant clause, and update the notice if the effect changes.

The hindrance register. Where the contract provides for a hindrance register, the contractor should ensure that each hindrance is entered, dated and signed or acknowledged by the employer's representative. A register that was never signed, or that was prepared after the event, carries much less weight.

Contemporaneous records. The strongest claims are built from documents made at the time, including:

  • The baseline programme and every revised programme
  • Daily progress reports and site diaries
  • Labour and equipment returns
  • Correspondence, requests for information and minutes of meetings
  • Drawing registers showing the dates drawings were requested and issued
  • Photographs and site measurements
  • Cost records, payroll and invoices

Delay analysis. For significant claims, a tribunal will expect an analysis that links each hindrance to the critical path. A delay to an activity that had float may not have delayed completion at all, and therefore may not support a claim for prolongation.

Defences an employer may raise

Defence What it means
Late or no notice The contractor failed to comply with the notice and claims procedure
No causation The hindrance did not delay the critical path, or the loss was caused by something else
Concurrent delay The contractor was also responsible for delay in the same period
Contractual exclusion The contract excludes claims for idle charges, overheads or specified heads, or contains a "no claim" clause
No proof of loss The contractor has not shown actual loss, only a formula
Waiver or accord The contractor accepted an extension without reservation, or signed a final bill with a full-and-final discharge
Failure to mitigate The contractor could have redeployed resources but did not

Exclusion and "no claim" clauses deserve particular care. Courts and tribunals have given them effect in many cases, but they have also declined to apply them where the delay arose from the employer's own default, or where the clause did not clearly cover the claim. The position depends on the wording and the facts, so it should be tested rather than assumed.

How to make a hindrance claim: a practical sequence

  1. Record the hindrance the day it occurs and enter it in the register or notice log.
  2. Give written notice under the contract, citing the clause and stating that the effect on time and cost will follow.
  3. Mitigate. Reallocate labour and plant where possible, and document what you did.
  4. Track the cost. Keep separate cost codes for hindrance-related expenditure.
  5. Update the programme to show the effect on completion.
  6. Submit the claim in stages, first for time and then for cost, with a delay analysis and supporting records.
  7. Reserve rights when accepting extensions or signing certificates, and avoid unqualified final bills or "no claim" certificates without taking advice.
  8. Seek advice early if the employer does not respond, and consider the dispute-resolution procedure in the contract before limitation or procedural bars apply.

What employers and developers should do

Employers are better served by treating hindrance claims as a risk-management matter, not as an adversarial one. Keep a register of what the employer was obliged to provide and when. Respond to notices in writing and promptly. Where a hindrance is genuinely the employer's responsibility, grant the extension that is due, which protects the right to levy liquidated damages for any delay that remains the contractor's. Where a notice is late or a claim is unsupported, say so in writing at the time, rather than leaving the point to be argued as a waiver at arbitration.

Illustrative scenario

This scenario is hypothetical and is included only to show how the points above fit together.

A contractor is engaged to build a hospital block under a twenty-four-month contract. The employer is to hand over the full site on day one and to issue the structural drawings for the upper floors by month six. In fact, one-third of the site is handed over in month five because of a dispute with a neighbouring owner, and the upper-floor drawings arrive in month ten. The contractor writes within two weeks of each event, refers to the relevant clause, logs the hindrances in the register (which the employer's engineer signs), and reallocates part of its workforce to other areas where possible. It keeps separate cost records for idle staff and equipment. At completion, the works are four months late. The contractor claims an extension of time, its extended site costs and a share of its head office overheads. A tribunal is likely to treat the first two heads, supported by the signed register and cost records, much more favourably than the third, which will depend on proof of lost opportunity. The same contractor, without notices or records, would have found that even the first two heads were hard to sustain.

Frequently asked questions

What is a hindrance claim in simple terms? It is a contractor's claim for extra time or money because the employer, or someone the employer is responsible for, obstructed or delayed the work.

Is a hindrance claim the same as an extension of time claim? Not exactly. An extension of time claim concerns the completion date. A hindrance claim often includes both time and the cost consequences of the obstruction.

What is a hindrance register? A record, commonly kept in public works contracts, in which obstructions to the work are logged with dates and acknowledged by the employer's representative. It is useful evidence of what happened and when.

Can a contractor claim head office overheads and loss of profit? Possibly, but the Supreme Court has required credible evidence that the delay caused a real loss, such as lost opportunities to take other work. A formula alone is generally not enough.

What if the contract has a "no claim" clause? Such clauses can limit or bar claims, but their effect depends on the wording and the circumstances. They should be reviewed carefully before a claim is abandoned.

Does late notice defeat a hindrance claim? It can, if the contract makes notice a condition of the claim. Even where it does not, late notice makes the claim harder to prove.

Which formula should be used to calculate overheads? There is no single mandated method. Hudson, Emden and Eichleay are commonly discussed, and the tribunal chooses based on the facts. The claimant must still prove that the assumptions behind the chosen formula are met.

Can an employer charge liquidated damages while a hindrance claim is pending? It may try to, but doing so while the extension remains undecided exposes the employer to challenge. Hindrance claims should be considered before delay damages are levied.

Sources

This article is for general information and is not legal advice. Contract terms differ, and each claim should be reviewed on its own documents and facts.