Power Purchase Agreements (PPAs) in India: Key Clauses and Legal Issues

By Ujjwal Sharma MCIArb · October 1, 2026 · 16 min read

By Ujjwal Sharma MCIArb, Sharma Kemp Chambers

A Power Purchase Agreement is, in a very real sense, the single document on which an entire power project stands or falls. Lenders finance against it, equity investors price their returns against its tariff, and the generator's twenty-five-year revenue projection depends entirely on the procurer honouring terms that were negotiated years before a single unit of electricity is dispatched. At Sharma Kemp Chambers, we advise both generators and procurers through the drafting of these agreements, and what strikes me most consistently is how often a dispute years into a project's life traces back to a clause that seemed entirely uncontroversial at signing, a change in law provision drafted too narrowly, a force majeure clause that never anticipated the specific disruption that eventually arose, or a payment security mechanism that looked robust on paper and proved considerably less so in practice.

This guide sets out the regulatory architecture governing PPAs in India, the clauses that genuinely determine how a project performs over its lifetime, and the legal issues that have, in recent years, tested these agreements most severely.

The Regulatory Architecture Behind Every Indian PPA

No PPA in India is negotiated in a vacuum. The Electricity Act, 2003 sits above every such agreement, and understanding how it shapes tariff determination is the necessary starting point before any individual clause can be properly assessed.

Section 61 sets out the broad principles the Appropriate Commission, the Central Electricity Regulatory Commission (CERC) for inter-State matters and generating stations, or the relevant State Electricity Regulatory Commission (SERC) for intra-State matters, must have regard to when regulating tariffs: commercial principles, the interests of consumers, efficiency, and the recovery of reasonable costs. From there, the Act offers two distinct routes to a tariff, and the difference between them shapes the entire character of the resulting agreement.

  Section 62 (Regulated Tariff) Section 63 (Competitive Bidding)
How tariff is set Determined by the Commission itself, having regard to capital cost, operating expenses, and a regulated return Discovered through a transparent, competitive bidding process; the Commission adopts rather than determines
Typical use State-owned or regulated generators, and projects without a competitive procurement mandate The dominant route for private generation, including the great majority of renewable energy capacity procured in recent years
Commission's role Active: scrutinises and sets the tariff components Largely passive: confirms the bidding process met the prescribed guidelines before adopting the resulting tariff
Tariff revision Periodically revisited through Multi-Year Tariff regulations Generally fixed for the PPA's tenure, subject to the agreement's own escalation, change in law, and force majeure provisions

This distinction matters well beyond the tariff-setting exercise itself. Where a PPA has been concluded under Section 63, the Supreme Court made clear in Energy Watchdog v Central Electricity Regulatory Commission (2017) 14 SCC 80 that the regulatory commission's role under Section 79 is to enforce the terms the parties themselves negotiated, not to rewrite them in the name of regulating tariff. A bidder who quotes a fixed, non-escalable tariff cannot later ask the Commission to revisit that commercial choice simply because external costs have risen, unless the agreement's own force majeure or change in law clauses genuinely apply on their terms. This single principle, that a competitively bid PPA is to be read and enforced as the parties wrote it, runs through almost every dispute discussed below.

Tariff and Payment Terms

The tariff clause itself, whether a single-part energy charge common to most renewable PPAs or a two-part structure combining a fixed capacity charge with a variable energy charge more typical of thermal generation, needs to state with precision how billing, metering, and invoicing actually operate in practice, not merely the headline rate. Ambiguity here, over which meter reading governs, how losses are accounted for, or what currency and escalation (if any) apply, is a remarkably common source of early-stage disputes that a more carefully drafted clause would have avoided entirely.

Payment Security: The Clause That Decides Whether the Tariff Is Worth Anything

A generator can negotiate an excellent tariff and still find the project in financial difficulty if the procurer simply doesn't pay on time, a risk that has materialised often enough in India's power sector that the Ministry of Power intervened directly. The Electricity (Late Payment Surcharge and Related Matters) Rules, 2022 now require every distribution licensee to maintain an unconditional, irrevocable, and adequate payment security mechanism, typically a letter of credit or a letter of credit backed by an escrow account, before power can be scheduled for supply at all. Where this security lapses, generators, transmission licensees, and trading licensees are entitled, and in practice obliged, to regulate (that is, reduce or suspend) supply to the defaulting distribution licensee, though a generator who continues supplying without the required security in place forfeits its own right to claim the late payment surcharge that would otherwise accrue.

For a generator negotiating a PPA today, this makes the payment security clause considerably less a matter of boilerplate than it once was. The agreement should specify the exact form of security (letter of credit, escrow, or both), the quantum it must cover, typically expressed as a multiple of average monthly billing, the mechanism's replenishment timeline, and the generator's rights where the procurer fails to maintain it, aligned closely with the LPS Rules rather than left to general contractual language that might sit awkwardly alongside the statutory regime.

Change in Law

A change in law clause allocates the risk of future legislative, regulatory, or fiscal changes between the parties, and Energy Watchdog remains the definitive word on how these clauses are read in India. The Supreme Court held that the meaning of "change in law" depends entirely on the specific wording the parties chose, not on some broader, implied notion of fairness or hardship, and, in the case before it, confirmed that a change in law clause referring generally to "law" meant Indian law, not the law of a foreign jurisdiction from which a generator happened to be sourcing fuel, however severely that foreign change affected the project's viability.

The practical lesson for drafting is to be exhaustive rather than general. A well-drafted change in law clause specifies precisely what counts as a qualifying change (new legislation, a change in an existing statute, a new or amended regulation or government order, or the imposition of a new tax or duty), the baseline date against which a change is measured, and the mechanism for calculating and passing through the resulting cost impact, typically through a tariff adjustment, rather than relying on a generically worded clause and hoping it will be read expansively if the need ever arises. Recent change in law disputes involving coal block cancellations, and the GST transition's impact on older PPAs executed before the tax was introduced, have both turned heavily on exactly this kind of textual precision.

Force Majeure

Closely related, but conceptually distinct, is the force majeure clause, which excuses performance (rather than adjusting tariff) where an event genuinely outside the affected party's control and reasonable control makes performance impossible. Energy Watchdog confirmed that force majeure in Indian PPAs operates against the backdrop of the Indian Contract Act, 1872, and that a party cannot invoke force majeure simply because performance has become more expensive or commercially unattractive; the event must render performance genuinely impossible, not merely onerous. A PPA's force majeure clause should, accordingly, list specific qualifying events (natural disasters, war, civil commotion, and similar) with reasonable precision, distinguish between events affecting the generator and events affecting the procurer, and set out clearly what relief follows, extension of time, suspension of obligations, or, in a sufficiently prolonged event, a right to terminate.

Curtailment and Must-Run Status

For renewable generators specifically, curtailment, the practice of instructing a generator to reduce or cease dispatch, usually for grid stability reasons, is one of the most commercially significant risks a PPA needs to address. The Electricity (Promotion of Generation of Electricity from Must-Run Power Plants) Rules, 2021 accord "must-run" status to most renewable generation, meaning load dispatch centres are not ordinarily entitled to curtail such plants except in defined grid security circumstances. In practice, this protection has required active enforcement: a well-publicised dispute in Andhra Pradesh saw renewable generators successfully resist curtailment that disregarded their must-run status, a position APTEL and the Supreme Court have generally upheld, and the Supreme Court's earlier ruling in Gujarat Urja Vikas Nigam Ltd v Solar Semiconductor Power Company (India) Pvt Ltd (2017) 16 SCC 498 reinforced the broader principle that a PPA, once concluded, cannot be unilaterally rewritten by a state government or distribution licensee acting outside the agreement's own terms, however commercially inconvenient the tariff has subsequently become for the procurer.

A PPA for a renewable project should, accordingly, state clearly that the plant carries must-run status in accordance with applicable regulation, specify the narrow circumstances in which curtailment is nonetheless permitted, and, critically, provide for compensation, commonly calculated by reference to deemed generation, where curtailment occurs outside those permitted circumstances. Leaving this to general regulatory entitlement, without a specific contractual compensation mechanism, has been a recurring source of prolonged, resource-intensive litigation for generators who were, in principle, entitled to protection all along.

Deemed Generation

Related to curtailment, but broader in scope, a deemed generation clause addresses what happens when a generator is ready, willing, and able to supply power but is prevented from doing so by a cause attributable to the procurer, whether grid unavailability, a failure of evacuation infrastructure, or an unlawful curtailment instruction. Without this clause, a generator bears the full revenue loss for an outage it did nothing to cause; with it, the generator is compensated as though generation had actually occurred, calculated against a defined methodology, typically historical generation data or plant load factor projections, that the PPA itself should specify rather than leave for later dispute.

Termination and Events of Default

A PPA's termination provisions need to address both parties' potential defaults with equal care, since the consequences, and the appropriate remedies, differ meaningfully depending on which side has defaulted.

  Generator Event of Default Procurer Event of Default
Typical triggers Persistent failure to achieve or maintain commercial operation, prolonged unauthorised outage, insolvency, breach of material obligations Persistent payment default, failure to maintain the payment security mechanism, wrongful or unlawful curtailment, insolvency
Usual procurer/generator remedy Termination, draw on performance security, appointment of a substitute generator Termination, payment of a termination compensation reflecting the generator's stranded investment, continued payment security claims
Lender interest Lenders typically require a defined cure period and step-in rights before termination for generator default takes effect Lenders are equally concerned with procurer default, since recurring payment failure threatens the project's debt service capacity directly

Termination compensation deserves particular attention in drafting, since a formula that undercompensates a generator for a procurer-side default (or, conversely, one that is unrealistically generous against a generator-side default) becomes a significant point of contention exactly when the relationship has already broken down and goodwill is in shortest supply. Well-drafted PPAs calculate this compensation by reference to a clear, pre-agreed formula tied to outstanding debt, equity investment, and any applicable discount, rather than leaving it to be negotiated, or litigated, after the fact.

Lenders' Step-In Rights

Because the great majority of Indian power projects are substantially debt-financed, lenders invariably require direct contractual rights against the procurer, most commonly through a tripartite agreement or a dedicated clause within the PPA itself, allowing them to step in and either cure a generator default themselves or substitute a replacement generator before the procurer can terminate the agreement outright. A procurer negotiating a PPA should expect this request and treat it as a standard feature of project-financed transactions, while still insisting on reasonable cure periods and notice requirements that don't leave genuine, non-curable defaults unresolved indefinitely.

Connectivity and Evacuation Infrastructure

A PPA should specify, with precision, which party bears responsibility for the transmission and evacuation infrastructure connecting the generator to the grid, the timeline for its commissioning, and the consequences, typically an extension of the scheduled commercial operation date, or deemed generation, where delay in that infrastructure (rather than the generation asset itself) is what prevents timely dispatch. This is an area where responsibility is genuinely shared across the generator, the transmission utility, and sometimes the procurer, and a PPA that assumes the generator bears all delay risk regardless of cause is both unrealistic and, in practice, difficult to enforce against a generator who was never responsible for the delay in the first place.

Tenure, Extension, and Dispute Resolution

Most Indian renewable PPAs run for twenty-five years, reflecting the asset's expected operating life and the debt tenor typically underpinning project financing, while conventional thermal PPAs vary more by project structure. The agreement should address what happens at expiry, whether extension on mutually agreed terms, a right of first refusal, or a clean termination, since a PPA silent on this point leaves both parties negotiating from scratch at precisely the point the relationship's value is best understood by both sides.

On dispute resolution, most Indian PPAs route disputes first to the Appropriate Commission under Section 86(1)(f) of the Electricity Act, 2003, which gives SERCs (and CERC, correspondingly) jurisdiction to adjudicate disputes between licensees and generating companies, with appeal to the Appellate Tribunal for Electricity (APTEL) and, from there, the Supreme Court under Section 125. Some PPAs additionally provide for arbitration of specific categories of dispute, though the interplay between contractual arbitration clauses and the regulatory commission's statutory jurisdiction under the Electricity Act has itself been a source of litigation, and this is a point worth addressing explicitly, and carefully, in drafting rather than assuming the two mechanisms will sit comfortably alongside one another by default.

Legal Issues That Have Tested Indian PPAs in Practice

Beyond individual clause drafting, a handful of broader, recurring disputes are worth understanding, since they shape how a prudent party now approaches negotiation.

Distribution company payment delays have been, for much of the past decade, the single largest practical risk facing Indian generators, prompting the LPS Rules discussed above and making the payment security clause considerably more central to PPA negotiation than it was a decade ago.

Attempts by state governments to retrospectively renegotiate tariffs, most notably the widely reported 2019 episode in Andhra Pradesh, where the state sought to revise previously agreed solar and wind tariffs downward and threatened termination if generators refused, have been firmly resisted by the courts on the straightforward basis that a state government is not a party to the PPA and has no standing to unilaterally alter its terms, however politically or fiscally attractive doing so might appear. This episode has, if anything, reinforced generators' confidence in the enforceability of properly negotiated, competitively bid tariffs, while also underscoring why the dispute resolution and jurisdiction clauses discussed above deserve genuine attention rather than routine adoption from a precedent document.

Curtailment disputes, addressed above, continue to require active vigilance from renewable generators, since must-run status, while legally robust, has in practice required litigation, and sustained engagement with load dispatch centres, to enforce consistently across states with varying degrees of compliance.

A Practical Checklist for Negotiating Parties

  • Treat the payment security clause as a live, commercially significant provision, aligned precisely with the LPS Rules, 2022, rather than a standard-form paragraph carried over from an earlier agreement.
  • Draft change in law and force majeure clauses exhaustively, not generally, naming specific qualifying events and mechanisms rather than relying on broad language that a court will, per Energy Watchdog, read narrowly and literally rather than expansively.
  • For renewable projects, build a specific compensation mechanism for unlawful curtailment into the agreement itself, rather than relying solely on the general statutory protection the Must-Run Rules already provide.
  • Negotiate termination compensation formulae early and in detail, since this is precisely the clause both parties will scrutinise most closely once the relationship has already broken down.
  • Address lenders' step-in rights proactively if project financing is anticipated, since retrofitting these protections into an already-executed PPA is considerably more difficult than negotiating them at the outset.
  • Be deliberate about the dispute resolution clause, considering carefully how it interacts with the Appropriate Commission's statutory jurisdiction under Section 86(1)(f) rather than assuming a generic arbitration clause will operate cleanly alongside it.

Conclusion

A Power Purchase Agreement carries weight far beyond its length on the page: it is the single instrument that determines whether a twenty-five-year power project is bankable, resilient to regulatory change, and capable of surviving the inevitable disputes that arise over a period that long. The clauses that matter most, payment security, change in law, force majeure, curtailment, and termination, are precisely the ones that reward careful, specific drafting over reliance on precedent language that may never have been tested against India's current regulatory and commercial realities. Getting these right at the negotiation stage remains, overwhelmingly, cheaper and more reliable than resolving a dispute over their meaning once a project is already operating and the stakes have grown considerably higher.

Need Advice on a Power Purchase Agreement?

Contact Ujjwal Sharma MCIArb at Sharma Kemp Chambers for more information. We advise generators, procurers, and lenders across the power and renewable energy sector in India.

Sources

  1. The Electricity Act, 2003, Government of India Legislative Department
  2. Electricity (Late Payment Surcharge and Related Matters) Rules, 2022, Ministry of Power
  3. Electricity (Promotion of Generation of Electricity from Must-Run Power Plants) Rules, 2021, Ministry of Power
  4. Indian Contract Act, 1872, Government of India Legislative Department
  5. Supreme Court of India, Energy Watchdog v Central Electricity Regulatory Commission, (2017) 14 SCC 80
  6. Supreme Court of India, Gujarat Urja Vikas Nigam Ltd v Solar Semiconductor Power Company (India) Pvt Ltd, (2017) 16 SCC 498

FAQs

What is the difference between a PPA concluded under Section 62 and one concluded under Section 63 of the Electricity Act?

Under Section 62, the Appropriate Commission actively determines the tariff having regard to the generator's costs and a regulated return. Under Section 63, the tariff is discovered through a competitive bidding process, and the Commission's role is largely confined to adopting that outcome, provided the bidding followed the prescribed guidelines. Most private and renewable generation in India today is procured under Section 63.

Can a distribution company unilaterally revise a tariff it has already agreed under a PPA?

No. Indian courts have consistently held that neither a distribution licensee nor a state government, which is not itself a party to the agreement, can unilaterally alter a validly concluded PPA. This principle was firmly reinforced during the 2019 Andhra Pradesh tariff renegotiation episode, where courts rejected the state's attempt to revise previously agreed tariffs downward.

What counts as a "change in law" event under an Indian PPA?

This depends entirely on how the specific clause is drafted. Following Energy Watchdog v CERC (2017), Indian courts read change in law clauses narrowly and literally, according to their actual wording, rather than expansively. A clause referring generally to "law" will generally be read as referring to Indian law only, which is why precise, exhaustive drafting of qualifying events matters considerably more than relying on broad or generic language.

What is "must-run" status, and does it guarantee a renewable generator will never be curtailed?

Must-run status, conferred on most renewable generation under the Electricity (Promotion of Generation of Electricity from Must-Run Power Plants) Rules, 2021, means a plant cannot ordinarily be curtailed except in defined grid security circumstances. It is a strong legal protection, but enforcing it in practice has sometimes required active litigation against load dispatch centres, which is why a well-drafted PPA should include its own specific compensation mechanism for unlawful curtailment, rather than relying solely on the general regulatory protection.

What is a payment security mechanism, and why does it matter so much in current PPA negotiations?

A payment security mechanism, typically a letter of credit or an escrow-backed letter of credit, is the financial guarantee a distribution licensee must maintain to secure its payment obligations under the PPA. Since the Electricity (Late Payment Surcharge and Related Matters) Rules, 2022 came into force, maintaining this mechanism is a precondition for continued power supply, making it one of the most commercially significant clauses in any current PPA negotiation, rather than a standard administrative formality.

How long do Indian PPAs typically run, and what happens when they expire?

Most renewable energy PPAs in India run for twenty-five years, broadly matching the asset's operating life and the typical debt tenor for project financing. What happens at expiry, extension, a right of first refusal, or termination, should be addressed explicitly in the agreement itself, since leaving this open invites a difficult renegotiation precisely when both parties' leverage is hardest to predict.